Bid Sheets 2009
December 18thInvitation for Bids December 18, 2009Plan holders listing for letting of December 18, 2009Addendum No. 1 December 18, 16, 2009Addendum No. 2 December 18, 2009Addendum No. 3 December 18, 2009Apparent Bid Results for Letting of December, 18 2009
November, 20thInvitation for Bids November 20, 2008Plan holders listing for letting of November, 20 2009Addendum No. 1 November, 20, 2009Apparent Bid Results for Letting of November, 20, 2009
October 16thInvitation for Bids October, 16 2009Plan holders listing for letting of October, 16 2009Addendum No. 1 October, 16, 2009Addendum No. 2 October, 16 2009Addendum No. 3 October, 16 2009Apparent Bid Results for Letting of October, 16, 2009
September 18thInvitation for Bids September 18, 2009Plan holders listing for letting of September 18, 2009Addendum No. 2 September 18, 2009Addendum No. 3 September 18, 2009Addendum No. 4 September 18, 2009Apparent Bid Results for Letting of September 18, 2009
August, 21stInvitation for Bids August 21, 2008Plan holders listing for letting of August 21, 2009Addendum No. 2 August 21, 2009Addendum No. 3 August 21, 2009Apparent Bid Results for Letting of August 21, 2009
August 14thInvitation for Bids August 14, 2009Plan holders listing for letting of August 14, 2009Addendum No. 1 August 14, 2009
July 17thInvitation for Bids July 17, 2009Plan holders listing for letting of July17, 2009Addendum No. 1 July17, 2009Addendum No. 2 July17, 2009Apparent Bid Results for Letting of July 17, 2009
June, 19thInvitation for Bids June 19, 2008Apparent Bid Results for Letting of June 19, 2009
June 12Invitation for Bids June 12, 2009Plan holders listing for letting of June 12, 2009Addendum No. 1 June 12, 2009Addendum No. 2 June 12, 2009
May 29Invitation for Bids May 29, 2009Plan holders listing for letting of May 29, 2009Addendum No. 1 May 22, 2009Apparent Bid Results for Letting of May 19, 2009
May 22Invitation for Bids May 22, 2009Plan holders listing for letting of May 22, 2009Addendum No. 1 May 22, 2009Apparent Bid Results for Letting of May 15, 2009
May 15Invitation for Bids May15, 2009Plan holders listing for letting of May 15, 2009Addendum No. 1 May 15, 2009Addendum No. 2 May 15, 2009Apparent Bid Results for Letting of May 15, 2009
April 17Invitation for Bids April 17, 2009
|
Project 1 |
US 285, MP 356.100 to MP 371.600 located in Taos County | CN: 5100070 NH-285-1(21)356 |
Project 2 |
US 82, MP 86.062 to MP 86.356 located in Eddy County | CN: 2100030 TPE-082-1(27)86 |
Project 3 |
NM 249, MP 0.000 to MP 1.050 located in Chaves County | CN: L2039/M200089 TPE-1231(7)/SP-2-09(361) |
Project 4 |
NM 209, MP 12.500 to MP 19.720 located in Curry County | CN: D2047 TPM-209-1(23)12 |
April 3
Invitation for Bids April 3, 2009
Addendum No. 1 April 3, 2009
Addendum No. 2 April 3, 2009
Addendum No. 3 April 3, 2009
Addendum No. 4 April 3, 2009
Plan holders listing for letting of April 3, 2009
Apparent Bid Results for Letting of April 3, 2009
Project 1 |
US 84/285, MP 184.910 to MP 186.180 located in Santa Fe County | CN: G1955 |
March 20Invitation for Bids March 20, 2009Addendum No. 1 March 20, 2009Plan holders listing for letting of March 20, 2009Apparent Bid Results for Letting of March 20, 2009
March 13Invitation for Bids March 13, 2009Addendum No. 1 March 13, 2009Addendum 2 No. March 13, 2009Apparent Bid Results for Letting of March 13, 2009
February 27thInvitation for Bids February 27, 2008Plan holders listing for letting of February 27, 2009Apparent Bid Results for Letting of February 27, 2009
February 20thInvitation for Bids February 20, 2008Plan holders listing for letting of February 20, 2009Addendum No. 1 February 12, 2009Apparent Bid Results for Letting of February 20, 2009
JanuaryInvitation for Bids January 16, 2008Plan holders listing for letting of January 16, 2009Apparent Bid Results for Letting of January 16th 2009
|
Economic Recovery Projects
Letting Schedule
Below is our draft letting schedule dated 02/12/09. This is the schedule we will be going by but is still subject to change.
The schedule was built around an estimate of roughly $200m that DOT will get in discretionary funding along with additional amounts from our regular program. It also includes timelines for bidding projects in Feb, Mar and Apr to meet a 90 day deadline for getting 50% of stimulus funding under contract.
The far right column indicates bid dates. These dates are in addition to our normal monthly bid dates.
I’ll be updating you as we adjust this schedule.
Mike Gibson
Associated Contractors of New Mexico
Economic Recovery Projects Letting Schedule PDF
Please see the following:
Robert Ortiz asked me to respond to you regarding the 2 week advertisement period for the Economic Recovery Projects. 23 CFR § 635.112 Advertising for Bids and proposals, paragraph (b) discusses the advertisement period for approved plans, specifications and estimates as being a minimum of 3 weeks prior to bid opening except that shorter periods may be approved by the Division Administrator in special cases when justified.
In accordance with the provisions of 23 CFR § 635.112, the NMDOT Chief Engineer Max Valerio submitted a request to the FHWA New Mexico Division Administrator requesting a two week advertising period for all projects anticipated to be funded with funding from the Economic Recovery and Reinvestment Package.
We received a verbal approval followed by a written approval on February 10, 2009 from FHWA to advertise the projects in the February 27, 2009 bid letting for two weeks beginning today, February 13, 2009.
If you should have any questions on this subject, please feel free to contact me, Robert Ortiz or Max Valerio.
Tamara P. Haas
Deputy Chief Engineer
Phone: (505) 827-3213
Cell: (505) 795-2126
Economic Recovery Projects Letting Schedule
| CN | Route, Location, Description | District | First Advertisement | Bid Date |
|---|---|---|---|---|
| G1945 | US 84/285 MP 187 to MP 189 | 5 | 13-Feb-09 | 27-Feb-09 |
| G5b07 | US 491 Tohatchi to Shiprock MP 15-29 Southbound | 6 | 13-Feb-09 | 27-Feb-09 |
| G7032 | US 62/180, MP 6-26 | 2 | 13-Feb-09 | 27-Feb-09 |
| G2132 | NM 128, MP 22-38.5 | 2 | 27-Feb-09 | 13-Mar-09 |
| G4013 | I-40 Paseo del Volcan/West Central Interchange MP 150-151 | 3 | 27-Feb-09 | 13-Mar-09 |
| G1955 | US 84/285 Mp 186-188 | 5 | 13-Mar-09 | 27-Mar-09 |
| G7042* | US 62, Texas Stateline to Carlsbad, MP 16-26 Recon SB lanes | 2 | 13-Mar-09 | 27-Mar-09 |
| G2a13 | I-25 Tramway to Bernalillo | 3 | 20-Mar-09 | 03-Apr-09 |
| G4084 | US 64 Raton to Clayton, Wetland Mitigation | 4 | 10-Apr-09 | 24-Apr-09 |
| G4034 | US 64 Raton to Clayton MP 378-390 | 4 | 10-Apr-09 | 24-Apr-09 |
| G1925* | US 84 Pojoaque to Espanola South Arroyo MP183 to MP185 | 5 | 10-Apr-09 | 24-Apr-09 |
| G1975* | US 84 Pojoaque to Espanola South Arroyo MP182 to MP183 | 5 | 10-Apr-09 | 24-Apr-09 |
| G18a2 | I-10, from the I-25 Interchange to Texas State Line | 1 | 24-Apr-09 | 08-May-09 |
| G5b66 | US 491 Tohatchi to Shiprock MP 59-67 | 6 | 24-Apr-09 | 08-May-09 |
| G2622 | US 380, Priest Gulch Bridge | 2 | 21-Aug-09 | 18-Sep-09 |